Project Online
Import Project Online plans into a new tool
Your Project Online exports still work after the retirement. Open each .mpp file in Project desktop, save it as XML, and import the XML into the new tool. Then check dependencies, calendars and custom fields, because no import keeps everything.
Last checked: 9 October 2026.
Which files you have
| File | What to do with it |
|---|---|
| .mpp | Open it in Project desktop and save it as XML. Most tools outside Microsoft cannot read .mpp directly, Teamhood included. |
| XML (MS Project XML) | Import it as it is. This format carries the task outline, dates and dependency links. |
| Excel or CSV | Import it as a list. Check the links: exports from the reporting feeds can miss task dependencies. |
You need Project desktop for one step
Project desktop does not retire with Project Online and still opens .mpp files. Check your version:
- Project 2021: support ends on 13 October 2026.
- Project 2024: supported until 9 October 2029.
- Planner and Project Plan 3 includes Project desktop.
No Project desktop at all? Use your Excel or CSV exports instead, and relink the dependencies after import.
Import a plan into Teamhood
- Save as XML. Open the plan in Project desktop. Choose File, Save As, and set the type to XML Format (*.xml).
- Start the import. In Teamhood, select + at the top of the sidebar, then Import. Drop the XML file. It can be up to 10 MB.
- Place the tasks. Pick the item type the tasks become. By default, the tasks go under one item named after the plan.
- Map and review. Map columns such as duration, work, % complete, priority, milestone, WBS and deadline to fields. Check the people the import could not match, then import.
Full steps: Import a plan from MS Project.
What the import keeps, and what it leaves out
| Keeps | Leaves out |
|---|---|
| Every task, nested as in the plan’s outline | Constraints, such as Start No Earlier Than |
| Start and finish dates | Calendars, working time and holidays |
| Predecessor links of all four types, with lag rounded to whole working days | Baselines, costs and custom fields |
| Task notes, as the item’s description | Material and cost resources |
| Assigned resources, matched to people and teams by name | Resources whose names match nobody (listed for you to fix) |
After the import: a short checklist
- Dependencies. Open the Gantt and check the links on the critical path.
- Dates. Calendars do not come across, so set people’s working weeks and time off, then check the dates that matter.
- Baseline. Save a new baseline once the plan looks right, so you can track changes from here.
- People. Fix the unmatched names from the import review.
- Fields. Recreate the custom fields you still need.
If you are moving to Planner instead
A Microsoft Q&A moderator answered in April 2026 that there is no native, automatic path from Project Web App to Planner premium. Importing .mpp files into Planner is not part of its main interface, and resources and baselines do not come across. Plan for the same checks either way.
Test one plan first
Import one real plan and check it against the list above before you move the rest.
First month free, no credit card.
Questions
Can Teamhood open an .mpp file?
Do dependencies survive the import?
Do baselines and custom fields come across?
What happens if we import the same plan twice?
We have no Project desktop. What now?
Sources
| Source | Used for |
|---|---|
| Teamhood help: Import a plan from MS Project | Steps, what the import keeps and leaves out |
| Microsoft Learn: Prepare for Project Online retirement | Project desktop after the retirement |
| Microsoft Lifecycle: Project 2021, Project 2024 | Desktop support dates |
| Microsoft Q&A 5846989 | Moving PWA plans to Planner premium (moderator answer) |
Change log: 9 October 2026, page published.