Project phase templates for HOAI, RIBA and SIA: free Excel downloads

Download a free Excel or CSV plan for the 9 HOAI work stages, the 8 RIBA Plan of Work stages or the 6 SIA 112 phases. Enter your total project hours and the HOAI version splits them by the official fee shares. For RIBA and SIA you enter your own shares. Each row has start, finish and owner columns.

Last updated: 25 October 2026. By Vidas Vasiliauskas.

On this page

  1. Download the templates
  2. The three schemes side by side
  3. HOAI: 9 work stages and their fee shares
  4. RIBA Plan of Work 2020: 8 stages
  5. SIA 112: 6 phases
  6. From phase scheme to a resourced plan

Disclosure: Teamhood makes project management software and wrote this guide. The phase names, outcomes and fee shares come from the official texts listed under Sources, read on 25 October 2026.

Download the templates

Each file is a plain project plan with one row per phase. In the Excel files, enter the total hours for the project and a start date at the top. The planned hours, start and finish of each phase then fill in. The durations in weeks are placeholders, so change them to your own. The CSV files list the phases only, for an import.

SchemeExcelCSVWhat is inside
HOAI (German)Leistungsphasen (.xlsx).csv7 sheets, one per service: buildings, interiors, landscape, civil structures, traffic, structural design, building services
HOAI (English)Work stages (.xlsx).csvThe same 7 sheets, with the German stage names and an English translation
RIBA Plan of Work 2020Stages 0 to 7 (.xlsx).csv8 stages with the RIBA stage outcome. The fee share column is empty for you to fill.
SIA 112Phases (.xlsx).csv6 phases and the sub-phases Swiss public clients use, with their goals. The fee share column is empty.

A German version of the SIA file is also available: SIA Phasen (.xlsx) and .csv.

The three schemes side by side

All three split a building project into phases with a clear result at the end of each one. They differ in how many phases they use and in whether they attach a fee share to each phase. Austrian phase models (LM.VM) are not covered here.

SchemeWhere it is usedPhasesFee share per phase
HOAI 2021Germany9 work stages (Leistungsphasen)Yes, set in the regulation for each service.
RIBA Plan of Work 2020UK8 stages, 0 to 7No. The Plan of Work sets outcomes and tasks per stage.
SIA 112Switzerland6 phases with numbered sub-phasesIn the SIA service standards, which are not public

HOAI: 9 work stages and their fee shares

Since 2021 the HOAI fee tables are orientation values. The fee is what the contract says in writing. Without a written agreement, the base rate applies. The split by work stage is still the common starting point for a phase budget.

The shares below are the percentages of the fee for each work stage, from the HOAI text. They split the fee. Real effort differs: detailed design (stage 5) can take more than its share. Adjust them with the hours your own past projects used. Interiors and traffic installations are in the downloads too.

Work stageBuildings (§ 34)Landscape (§ 39)Civil structures (§ 43)Structural design (§ 51)Building services (§ 55)
1 Grundlagenermittlung (establishing the basis)2%3%2%3%2%
2 Vorplanung (preliminary design)7%10%20%10%9%
3 Entwurfsplanung (final design)15%16%25%15%17%
4 Genehmigungsplanung (planning permission)3%4%5%30%2%
5 Ausführungsplanung (detailed design)25%25%15%40%22%
6 Vorbereitung der Vergabe (preparing the tender)10%7%13%2%7%
7 Mitwirkung bei der Vergabe (assisting with contract award)4%3%4%not included5%
8 Objektüberwachung or Bauoberleitung (site supervision)32%30%15%not included35%
9 Objektbetreuung (aftercare)2%2%1%not included1%

Some shares can change by contract. For civil structures, work stage 5 may be agreed at 15 to 35% when the execution drawings take more work than usual. For structural design, work stage 5 drops to 30% or 20% in the cases § 51 lists. A reform is on the way: the AHO’s conference on 24 November 2026 is titled “HOAI 2027 auf der Zielgeraden”. Check the current text before you put a share in a contract.

The HOAI annexes list the basic services per stage. Two of them matter for planning. Work stage 2 includes a first schedule of the planning and building process. Work stage 8 includes setting up and tracking a bar-chart schedule.

RIBA Plan of Work 2020: 8 stages

The RIBA Plan of Work is the UK framework for all disciplines on a building project. Projects run from stage 1 to stage 6. Stage 0 may end with the decision to start a project, and stage 7 covers the use of the building.

StageOutcome at the end of the stage
0 Strategic DefinitionThe best means of achieving the client requirements confirmed
1 Preparation and BriefingProject brief approved by the client and confirmed to fit the site
2 Concept DesignArchitectural concept approved by the client and aligned to the brief
3 Spatial CoordinationArchitectural and engineering information spatially coordinated
4 Technical DesignAll design information needed to manufacture and construct the project completed
5 Manufacturing and ConstructionManufacturing, construction and commissioning completed
6 HandoverBuilding handed over, aftercare started and building contract concluded
7 UseBuilding used, operated and maintained efficiently

Stages 4 and 5 overlap on most projects, so plan them as parallel bars. For the fee share column, use the share of hours your last three similar projects spent in each stage.

SIA 112: 6 phases

SIA 112 is the Swiss model for planning and building services. Public clients such as the City of Bern and the canton of Fribourg plan their projects in its phases and numbered sub-phases. The table uses their wording.

PhaseSub-phasesGoal
1 Strategische Planung (strategic planning)11 needs and solution strategiesNeeds, goals and constraints defined, solution strategy set
2 Vorstudien (preliminary studies)21 project definition and feasibility study, 22 selection procedureFeasibility shown, project specification written, provider or design selected
3 Projektierung (design)31 Vorprojekt, 32 Bauprojekt, 33 approval procedureProject approved, costs and dates verified, building credit approved
5 Realisierung (realization)51 construction design, 52 construction, 53 commissioning and close-outConstruction designed, built, commissioned and closed out

Phase 4 Ausschreibung (tendering) and phase 6 Bewirtschaftung (operation) complete the model. Their sub-phases are in the standard. The City of Bern points to SIA 103 and SIA 112 for the services engineers provide. Enter the fee shares from your own copy of the standard.

From phase scheme to a resourced plan

The templates list phases and hours. These five steps add people and capacity.

  1. Turn the fee into hours. Take your profit margin and subconsultant costs off the agreed fee. Divide the rest by your average hourly rate. That gives the total hours the fee pays for. Enter it at the top of the template.
  2. Split the hours by phase. The HOAI shares do this for you. Keep a reserve for changes the client asks for.
  3. Assign people and check their capacity. Your engineers work on several projects at once. Check their planned hours across all projects, with holidays and part-time weeks, before you commit dates to the client.
  4. Save a baseline. When the client signs off the schedule, save it. Later you can show what moved and why.
  5. Re-plan every week. Compare logged hours per phase with the phase budget. A phase that has used 80% of its hours at 50% done needs a decision that week.

Plans slip often in this industry. IW Consult surveyed German planning offices in 2025 for AHO, BAK, VBI and BIngK. In work stages 1 to 5, 74% reported projects running longer than agreed. In stages 6 to 8 it was 81.2%.

Where Teamhood fits

Teamhood is project management software with Kanban, Gantt and timesheets, for firms that run many projects with the same people. It imports CSV files and the XML file MS Project saves, so use the CSV version of a template for an import.

Any item type can have templates, including projects. A project template keeps its tasks, so you set up your HOAI or RIBA plan once and reuse it. Dates in a template count in working days from the day you create the project.

The Gantt has dependencies, critical path and baselines. Capacity counts each person’s planned hours across every project, with time off. A budget can be in hours or in money, and each project shows its cost against its budget. Teamhood is hosted in the EU on Microsoft Azure. It costs €11 per user per month, billed yearly, or €14 billed monthly, excluding VAT. The first month is free.

What Teamhood does not do

  • Teamhood cannot read an .mpp file. Save the plan as XML in MS Project first.
  • The MS Project import leaves out constraints, calendars, baselines, costs and custom fields. Lag is rounded to whole working days.
  • No mobile app. Teamhood runs in the browser.

Questions

Can I use the templates without Teamhood?
Yes. They are plain Excel and CSV files with no macros and no account needed. They open in Excel, LibreOffice and Google Sheets.
How do I plan HOAI work stages 5 and 8 when they overlap with construction?
Plan them as parallel bars with their own hour budgets. Detailed design often continues while the site works on earlier packages. Tie each design package to the site work it feeds with a dependency.
What columns does the CSV file have?
The English HOAI file has Service, Section, Stage, Leistungsphase, English, Share of fee (%), Main results, Planned hours, Start, Finish and Owner. The last four columns are empty. The RIBA and SIA files have the stage or phase, its outcome or goal, and the same planning columns.

Sources

  1. HOAI § 34 Gebäude und Innenräume, § 39, § 43, § 47, § 51 (including Abs. 2 and 3), § 55. Read 25 October 2026.
  2. HOAI § 2a and § 7 (orientation values, fee agreement). Read 25 October 2026.
  3. HOAI Anlage 10 (basic services per stage, buildings). Read 25 October 2026.
  4. AHO Herbsttagung 2026, program (PDF). Read 25 October 2026.
  5. RIBA Plan of Work and the 2020 template (PDF). Read 25 October 2026.
  6. Canton of Fribourg, civil engineering office: phases and sub-phases (SIA 112, VSS 40 026), PDF. Read 25 October 2026.
  7. City of Bern, Fachordner Wasserbau: Realisierung (PDF). Read 25 October 2026.
  8. Mitgliederbefragung 2025 zur wirtschaftlichen Situation der Architektur- und Ingenieurbüros (PDF). IW Consult for AHO, BAK, VBI and BIngK, 2,452 offices. Read 25 October 2026.
  9. How templates work, Import a plan from MS Project, Teamhood facts.