How to spot delays across multiple projects

Delays show first in the links between work. Watch for a predecessor that finishes late, a critical path that changes, float that runs out, a finish that slips against the baseline and a person booked past capacity. Check all of them every week, in every project.

Last updated: 26 October 2026. By Vidas Vasiliauskas.

Early warnings, in the order they appear

  1. A predecessor finishes late. With linked dependencies, the work that waits on it moves too. Without links, the plan keeps the old dates and nobody sees which tasks are now late.
  2. The critical path changes. A task that had float becomes critical. The project finish now depends on it.
  3. Float runs out. Total float is the number of working days a task can finish later before the project finishes later. When it reaches zero, the next day of delay moves the finish.
  4. The finish slips against the baseline. A saved baseline shows how many days each task has moved.
  5. A task runs past its summary task. The summary date in the client report is no longer true.
  6. A person is overbooked on the days the work needs them. The dates can look fine while the person has no time to do the work.

The first warnings come weeks before the last ones. A team that reviews only the finish date sees the delay when it is hard to fix.

A weekly portfolio review

  • Sort open tasks in all projects by total float, lowest first.
  • List tasks whose finish moved since the baseline, per project.
  • Check links between projects.
  • Check capacity for the next 2 to 4 weeks for the people on critical tasks.
  • Give each late task an owner and one next action.
  • Save a new baseline only when a new date is agreed with the client.

How common tools show delays

ToolWhat it showsNotes
Jira (Plans)In the dependencies view of a plan, an arrow turns red when a dependency is off track.The dependencies view is on Jira Cloud Premium and Enterprise.
Microsoft ProjectCritical tasks get red Gantt bars. You set how much slack makes a task critical. Up to 11 baselines per project.By default it shows only one critical path.
SmartsheetCritical path tasks are red in the Gantt view. A baseline adds Baseline Start, Baseline Finish and Variance columns.One baseline per sheet. Only sheet Owners or Admins create it. Baselines are on Pro, Business and Enterprise.
AsanaEach project has a status (on track, at risk, off track), picked by the person who posts the status update. AI can suggest a status. Timeline shows task dependencies.Advanced includes unlimited portfolios.
TeamhoodDependencies move the tasks that wait on them. Critical path drawn, other tasks faded. Total float per task. Baseline finish in red or green. Overbooked days turn red.No mobile app. Minimum 3 licenses.

Read on each vendor’s help or feature pages on 26 October 2026.

Where Teamhood fits

Teamhood fits firms that run many projects with the same people. When a task moves later or earlier, the tasks that depend on it move with it. A dependency can link tasks in different projects, so a late task in one project moves the tasks behind it in another.

The Gantt draws the critical path, fades the rest and shows the total float of each task in working days. A task that runs past its summary task shows in red. Save the plan as a baseline, and each bar shows whether it finishes later (red), earlier (green) or the same (gray). Start and finish variance can be shown as columns.

Planned hours count across every project, and overbooked days turn red. A portfolio view across projects is set up from lists and views.

Teamhood is hosted in the EU on Microsoft Azure. The price is €11 / $12 per user per month, billed yearly, excluding VAT. The first month is free, with no credit card. See pricing or all facts.

What Teamhood does not do

  • There is no mobile app. Teamhood runs in the browser.
  • Teamhood cannot read an .mpp file. The MS Project import leaves out constraints, calendars, baselines, costs and custom fields.
  • The smallest subscription is 3 licenses.

Questions

What is total float?
The number of working days a task can finish later before the project finishes later. A task with zero float is on the critical path.
Can a delay in one project move another project in Teamhood?
Yes, if the tasks are linked. A dependency can link tasks in different projects, and the tasks that depend on the late task move with it.
When should I save a new baseline?
When a new date is agreed with the client. Until then, compare against the original plan, so the variance shows how far the plan moved. A Teamhood baseline holds up to 5,000 tasks.
Is a status color enough for a portfolio review?
A status someone picks by hand shows what that person thinks. Float, baseline variance and capacity show what the plan says. Use both.

Sources

  1. Atlassian Support: the dependencies view in your plan. Red arrow, plans. Read 26 October 2026.
  2. Microsoft Support: show the critical path of your project. Read 26 October 2026.
  3. Microsoft Support: set and save a baseline. Read 26 October 2026.
  4. Smartsheet Help: baselines and critical path. Read 26 October 2026.
  5. Asana status updates and Asana pricing. Read 26 October 2026.
  6. Teamhood Help: dependency scheduling, Gantt view and baselines. Read 26 October 2026.
  7. Teamhood facts and What Teamhood does. Dependencies, Gantt, baselines, capacity and limits.