Utilisation rate for engineering and architecture firms: how to measure it and set targets
Utilisation is project hours divided by the hours a person is available after holidays and sick days. German planning offices report about 76% of working time on project work. Set a target per role from its non-project duties, plan below it, and compare planned with logged hours every week.
Last updated: 25 October 2026. By Vidas Vasiliauskas.
In this guide
- What utilisation measures
- How to calculate it
- What firms report
- Why 100% is the wrong target
- Set a target per role
- Planned and actual: the weekly review
- Common mistakes
Disclosure: Teamhood makes project management software and wrote this guide. Survey figures come from the publishers’ own documents, with the date we read them.
What utilisation measures
Available hours, also called capacity, are contract hours minus holidays, public holidays and sick days. Three numbers get called utilisation, and all three use capacity. Agree which one you mean before you compare anything.
- Utilisation. Hours on project work divided by capacity.
- Chargeability. Hours you can bill to a client divided by capacity. It is lower than utilisation when project work includes unbilled rework or fixed-fee overruns.
- Planned load. Hours already planned for a person in a coming week, divided by their capacity that week.
Only planned load can still be changed.
How to calculate it
Start with the hours a person can work at all. In Germany, 2024 had 252 working days. The IW survey for the German chambers counts from that number and deducts holidays and sick days.
The example below uses one engineer with a 40-hour week. The holiday and sickness figures are example values. Use your own.
| Step | Value | How |
|---|---|---|
| Working days in the year | 252 | Germany, 2024 |
| Holidays | 30 days | Example value |
| Sick days | 10 days | Example value |
| Days available | 212 | 252 minus 30 minus 10 |
| Capacity in hours | 1,696 | 212 days at 8 hours |
| Project hours logged | 1,300 | From timesheets |
| Utilisation | 77% | 1,300 divided by 1,696 |
The same hours set your hourly rate. Our hourly rate and overhead calculator turns capacity, utilisation and costs into a break-even rate.
What firms report
Three recent sources publish a figure. They measure in different ways, so compare your firm with one source at a time.
| Source | Who | Figure |
|---|---|---|
| IW Consult for AHO, BAK, VBI and BIngK, 2025 | German offices, n = 1,007 for this question | 76.5% of working time on project work (architects 78.3%, engineers 75.5%, median 80% for both). Self-reported. |
| Deltek Clarity, 2026 | 896 architecture and engineering firms, US and Canada | Utilisation under 60%, falling. The press release does not define the measure. |
| Monograph benchmarks, 2026 | 660 to 856 US firms per metric, the vendor’s own platform data | 81% average utilisation |
The German survey found no significant link between office size and project-time share. The 2024 BAK survey shows how much data is missing. Of 5,150 self-employed architects, 61% have project hours recorded systematically. In offices with more than 10 staff, 89% do.
Why 100% is the wrong target
A person planned at 100% has no hours free for change. Briefs change, authorities ask for more documents, and people get ill.
Project dates move often. In the 2025 IW survey, 74% of German offices said projects ran longer than agreed in HOAI work stages (Leistungsphasen) 1 to 5. In stages 6 to 8 it was 81.2%. The extra weeks fall to people who already have full plans.
High targets also make the timesheet data less reliable. In English-language architecture and engineering forums, staff at large firms describe targets of 85%. The top reply in one thread says such targets are reached with false timesheet entries.
Set a target per role
A single office-wide target is too high for partners and office leads. Work out each role’s target from its fixed non-project duties instead.
| Role (example) | Non-project share | Target |
|---|---|---|
| Partner or office lead | Acquisition, staff, finance: 45% | 55% |
| Project lead | Proposals, coordination, mentoring: 25% | 75% |
| Project engineer or architect | Training, internal meetings: 20% | 80% |
| Office and IT staff | Almost all of it | No target |
The shares are examples. Agree them with each person, write them down, and review them once a year. Keep planned load about 10 percentage points below the target, so there are hours free when a change comes.
Planned and actual: the weekly review
A weekly review of planned load shows an overload before the deadline.
- Check the next 4 weeks. Look at each person’s planned load against their capacity. Mark everyone above the target.
- Move the work. Shift a task, split it, or give it to someone with capacity. Do it while the deadline is still weeks away.
- Compare last week. Put logged hours next to planned hours per project. A project that used half its hours and is not half done needs a decision this week.
- Show the budget. Show each project team its hours budget per phase.
Keep the meeting to 30 minutes. The point is one decision per problem.
Common mistakes
- Counting contract hours as capacity. Holidays and sick days are not free time to fill. Utilisation then looks low, and the office plans too much work.
- Timesheets as a control tool. If logged hours decide bonuses, people log what is expected. Use them to check the fee, and say so.
- No time code for internal work. Without one, internal hours get booked to whichever project has budget left. Give meetings, training and proposals their own codes.
Where Teamhood fits
Teamhood is project management software with Kanban, Gantt and timesheets, for firms that run many projects with the same people. Each person has weekly working hours, part-time contracts and time off. Planned hours count across every project.
In the schedule view, grouped by person, each column shows planned hours against capacity. A cell turns red when the hours exceed it. Team lanes add up their members’ capacity. Teamhood has timesheets, with export.
A project budget can be in hours or in money. Tracked time adds up from tasks to the project, and a project shows its cost against its budget. Hourly cost rates price the logged hours.
Teamhood costs €11 / $12 per user per month, billed yearly, or €14 / $16 billed monthly. Prices exclude VAT. Hosted in the EU on Microsoft Azure. Our team moves your projects from Excel, MS Project or another tool at no extra cost. The app is in English.
What Teamhood does not do
- An AI assistant such as ChatGPT or Claude, connected to Teamhood, sees only the hours someone planned explicitly. It does not see the hours Teamhood spreads automatically from a task’s estimate.
- Teamhood cannot read an .mpp file. Save the plan as XML in MS Project first.
- Single sign-on (SSO), SCIM and a choice of region (EU, Germany or US) are on Enterprise only.
Questions
What is a good utilisation rate for an engineering firm?
Is utilisation the same as chargeability?
Should partners have a utilisation target?
How often should we review utilisation?
Do we need timesheets to measure utilisation?
Sources
- IW Consult for AHO, BAK, VBI and BIngK, Mitgliederbefragung 2025 (PDF). 2,452 German offices, April and May 2025. Read 25 October 2026.
- BAK Strukturbefragung 2024, self-employed members (PDF). Report year 2023. Read 25 October 2026.
- Deltek Clarity 2026 study, press release. Read 25 October 2026.
- Monograph 2026 A&E Business Benchmarks. Read 25 October 2026.
- r/civilengineering thread on utilisation targets and r/Architects thread. Read 25 October 2026.
- Teamhood schedule view, capacity and time off and Teamhood facts.