Microsoft Planner vs Project: what is the difference now?
Project is now sold as Planner plans and as a desktop app. Planner Plan 1 has a Timeline (Gantt), finish-to-start dependencies and a People view. Planner and Project Plan 3 adds critical path, baselines, all dependency types, a Capacity view, portfolios and the Project desktop app. For advanced portfolio management, Microsoft points to Project Server.
Last updated: 28 November 2026. By Vidas Vasiliauskas.
What changed in 2026
- Plan 5. Microsoft stopped selling Planner and Project Plan 5 on 1 May 2026. Existing customers may keep their subscriptions. Our Plan 5 end of sale guide lists what Plan 3 drops.
- Project Online. It retired on 30 September 2026. Our Project Online retirement guide covers your data.
- Project for the web. Microsoft’s docs say it becomes Microsoft Planner.
Prices for every plan, with totals for 10, 40 and 100 users, are on How much does Microsoft Project cost.
What each plan includes
| Feature | Planner in Microsoft 365 | Planner Plan 1 | Planner and Project Plan 3 |
|---|---|---|---|
| Timeline (Gantt) view | No | Yes | Yes |
| Finish-to-start dependencies | View only | Yes | Yes |
| Start-to-start, finish-to-finish, start-to-finish, lead and lag | View only | View only | Yes |
| Critical path | No | No | Yes |
| Baselines | No | No | Yes |
| People view | No | Yes | Yes |
| Assignments and Capacity views | No | No | Yes |
| Bookings for resource requests, skills on resources | Not listed | Not listed | View only |
| Portfolios | No | View only | Yes |
| Project desktop app | No | No | Yes, up to 5 PCs per user |
From the Planner service description on Microsoft Learn and Microsoft’s US Planner plans page, read 28 November 2026. Bookings and skills come with Plan 5, which is no longer sold.
Microsoft also publishes limits for premium plans. A plan holds up to 3,000 tasks, 300 resources, 2,000 links and 10 custom fields. These come from its Project for the web limits page, which Microsoft’s Planner help links to.
What a Project Online PMO has left
Microsoft’s retirement guide lists what stopped with Project Online. That includes Project Center, Resource Center, Timesheets, Project Detail Pages, resource management and portfolio analysis. The guide says a destination is not always a one-to-one replacement. Some firms use more than one.
Microsoft maps the work to its products like this:
- Planner. Collaborative planning, task management and portfolio visibility, in Teams.
- Project desktop. Schedule authoring, baselines and dependencies, resource and cost planning, .mpp files. Project Professional 2024 adds timesheets.
- Project Server Subscription Edition. On-premises, with advanced portfolio management and resource capacity management.
- Dynamics 365 Project Operations. When project delivery is tied to sales, finance and billing.
People who only update tasks can use Plan 1.
Options side by side
| Option | Price per user | Where it runs | What it covers | Limit |
|---|---|---|---|---|
| Planner Plan 1 | $10 / €8.70 a month, billed yearly | Browser and Teams | Timeline (Gantt), finish-to-start dependencies, People view | No critical path or baselines |
| Planner and Project Plan 3 | $30 / €26 a month, billed yearly | Browser, Teams and the desktop app | Critical path, baselines, Capacity view, portfolios | 3,000 tasks per plan. Bookings and skills are view only. |
| Project Professional 2024 | $1,129.99 / €1,659 once | One PC per license | Gantt, resource leveling, Team Planner, timesheets | Supported until 9 October 2029 |
| Project Server Subscription Edition | No list price | Your own servers | Portfolio analysis, resource and demand management | Bought through a partner. |
| Teamhood | $12 / €11 a month, billed yearly | Browser, any operating system | Critical path, dependencies across projects, baselines, planned hours across every project, timesheets, portfolio view | No .mpp files and no mobile app |
Microsoft prices from its US and German plans pages, read 28 November 2026. Planner prices exclude VAT. Microsoft’s Project 2024 page does not say.
Where Teamhood fits
Teamhood fits a PMO that plans the same people across many projects. Planned hours count across every project, so you see who has time before you commit them. A dependency can link items in different projects, so a late item in one project moves the items that depend on it in another. The Gantt draws the critical path, and a baseline holds up to 5,000 items. Teamhood is hosted in the EU on Microsoft Azure.
Teamhood imports the XML file MS Project saves, up to 10 MB. It keeps the task outline, dates, all four dependency types, notes and assigned people. Our team moves all your projects at no extra cost.
If you pay for another project tool, show us the contract. Teamhood is free until that contract ends, for up to 12 months, for as many licenses as that contract covers. You also get the free first month. See how the move works.
What Teamhood does not do
- Teamhood cannot read an .mpp file. Save the plan as XML in MS Project first.
- The MS Project import leaves out constraints, calendars, baselines, costs and custom fields. Lag is rounded to whole working days.
- No mobile app. Teamhood runs in the browser.
Questions
Is Planner premium a replacement for Project Online?
What does Planner and Project Plan 3 include?
Does Planner Plan 1 have a Gantt chart?
Can Plan 1 and Plan 3 users work in the same plan?
Sources
- Microsoft Learn: Planner service description. Features by plan, Plan 5. Read 28 November 2026.
- Microsoft Planner plans and pricing. Desktop app, plan features, user limits. Read 28 November 2026.
- Microsoft Project plans and pricing. Project 2024 and Project Server. Read 28 November 2026.
- Microsoft Support: Planner basic vs premium plans and Project for the web limits. Read 28 November 2026.
- Microsoft Learn: Prepare for Project Online retirement. Read 28 November 2026.
- Microsoft Lifecycle: Project 2024. Read 28 November 2026.
- Teamhood facts. Gantt, dependencies, baselines, capacity, switching offer, limits.